The stabling capacity at Lillestrøm will significantly increase and will be able to facilitate the new NSB Flirt trains.

Lillestrøm stabling

Implenia has implemented the extension of the stabling area at Lillestrøm station. The stabling capacity at Lillestrøm has significantly increased and is now able to facilitate the new NSB Flirt trains.

Lillestrøm stabling

Project scope. The project consisted of the substructure and railway engineering works for the extension of the Lillestrøm stabling. Old contaminated mass has been removed, a new substructure is established, new platforms constructed, a new water and sewerage system installed and new tracks and switch points have been built as well as new electrical and overhead line systems. Also included were upgrades to the substructure and tracks in the operations area for Jernbaneverket.

Increased capacity in Eastern Norway. In addition to increasing the stabling capacity at Lillestrøm, maintenance work is now simplified through new platforms, water and sewerage and train heating systems. The operations area is more accessible and easier to run. This project is one of a number of projects implemented to facilitate the upgrades to the timetable in Eastern Norway and the implementation of new sets of trains to increase capacity for passenger transport.

Project details:

  • Contract type: Prime contract
  • Contract sum: MNOK 105
  • Construction time: March 2012 to August 2014
  • Developer: Jernbaneverket
  • Client: Jernbaneverket

Technical information:

  • Excavation of approximately 12,000 m3
  • Subbase approximately 13,500 m3
  • Installation of open cable ducts, approximately 2700 m
  • Installation of cable routing in the ground, approximately 3000 m
  • Platforms and retaining walls, approximately 1500 rm
  • Asphalting, approximately 13,000 m2